1、Method statement for raw material silo. Project description1.0 Raw material silo:RCC silo, outside diameter is 23.472m.A cone starts at 8.693. Ring foundation is adopted. Concrete structure for the top. . References1.0 Drawings of raw meal homogenizing silo & kiln feeding system2.0 The construction
2、organization and design 3.0 The relative construction codes and regulations. Main construction method 1.0 Preparations1.1 Equipment: Mobilization and commissioning of tower crane, sliding devices, welder, etc, so as to ensure the slip form works in the normal way. 1.2 Materials: Work out the plan of
3、 steel and carry out the fabrication work, prepare the plan of concrete and other materials.1.3 Job site: Smooth and straight so as to ensure the convenience of material transportation.1.4 Adequate manpowers.2.0 Silo wall slip form construction2.1Slip form constructiona. ConcreteThe concrete adopted
4、 for this job will be ready mixed concrete. The following data shall be noted in the plan sheet: pouring and vibrating time, pouring section, strength requirement, slumps and the quantity (cubic meters) intended to be poured and planned time of pouring. When slipform starts, the concrete shall be co
5、ntinuous, and the masons follows to vibarte. The concrete will be put into formworks and vibrated at the same time from both directions, so as to avoid the occurrence of slots or cracks caused by the already hardened concrete when only work to one direction. The proper slump requirement for slipform
6、 is 90-140mm. Concrete transportation: the concrete in the self-fabricated tipcart will be transported by the headframe to the sliding platform, and supplied to place of pouring by the tipcart.Vertical transportation: After calculation, the capacity of the tower crane meets the actual transportation
7、 demand. At the same time vertical transportation of the concrete should meet the demand for different section, Therefore, three headframe, which could goes up with the platform, is needed for silo wall sliding up, and self-fabricated tipcart, actually the capacity of the lorry is 0.18 cubic meters.
8、 Concrete pouring: when the silo wall is sliding up, put the concrete from the tipcart onto the platform between two slip form supports, masons shovel all the concrete on the platform into the formwork, masons following to vibrate the concrete. The concrete shall be continuously, and put into formwo
9、rks and vibrated at the same time to both directions, so as to avoid the occurrence of slots or cracks caused by the already hardened concrete when only work in one direction.After put the concrete into the formwork, vibrate it in time with poker vibrator. The working principle is “quick insert and
10、slowly pull out”, “one vibrator after another”, “vibrating in parallel”. For each point, the vibrating time is 20s-30s, the vibration could not be stopped only when the concrete surface does not go down obviously, and there is no air bubble comes out, and thick liquid occurs on the concrete surface.
11、 When vibrating the upper layer, the insert to the lower layer could not more than 5cm and connection joints between these two layers shall be eliminated. No vibration and over vibration is forbidden.When concrete is delivered, slump should be checked. The proper slump for slip form construction is
12、90-140mm.Records must be taken and kept for the strength test, and mark out the pouring section and strength etc. The concrete shall be crushed at 7 and 28 days. When results are satisfactory, the documents shall be kept in the archives. As for the disqualified cubes, the reasons have to be found ou
13、t and actions for that batch have to be taken.b. ReinforcementThe vertical rebars lapping shall staggered at 1/4, and the overlapped area of ring horizontal rebars shall be no less than 50d. when the overlapping joints staggered distance is longer than 1000, then one rebar could be overlapped in the
14、 same area every four pieces. The rebars above the door and of the silo wall shall be bond when sliding up, the binding works shall be done with the concrete grouting one after the other.The concrete cover and position of the rebars are ensured to be correct by the clips installed in the horizontal
15、beam of the slip form supports.c. sliding-upPreliminary sliding-up: when begin with silo wall grouting, the concrete shall be grouted in 3 layers into the formwork of 1200mm on both directions. Try to slide up the wall after 4 or 5 hours with 2 to 4 courses. Test the concrete out of the formwork wit
16、h hand, when there is only a slight fingerprint and the concrete does not stick to the hand, then the normal sliding up procedure could be carried out after a short break.After completion of the soleplate construction, the above-mentioned method shall be taken for the grouting of upper silo wall. At
17、tention:When start constructing silo wall above the soleplate, please pay attention to see whether the concrete strength of the soleplate meet sliding-up requirement because the sliding-up will start immediately after finish soleplate grouting works. If the concrete is not strong enough, the sliding
18、-up speed shall be decreased. Normal sliding up: each time sliding up 30cm, the concrete shall be grouted circularly on both directions. It shall be lifted at an interval of 1.5-2.0 hours, and when the temperature is high, it could be lifted 1-2 courses additionally. Whenever sliding up, correction
19、works has to be done to avoid excursion and torsion, in case the deviation of the plummets for excursion and torsion controlling exceed 15mm (generally if any deviation occurs), correction works shall be done. Platform excursion: the level controlling of platform and formworks are the key point for
20、center controlling. Before sliding up the formworks, the whole platform and the level of the jack must be checked and corrected by water level. The support shall be checked by water level as well, it shall be checked every other grouting.Deviation of the platform shall be corrected by inclining, lif
21、t the jack on the deviated side to a proper height and sliding up when the platform is inclined (no more than 1%), after the deviation has been corrected, continue with normal sliding procedure. Platform torsion: torsion of the platform shall be corrected by dragging, 8 points shall be selected even
22、ly along the periphery and dragged by manual hoists to the opposite direction of the torsion, the torsion will be corrected when lift up the formwork.Attention:The poles must be reinforced when lifting up the platform without concrete.Stop sliding: when the sliding up must be stopped due to construc
23、tion necessity or special cases, it shall be lifted up 1-2 courses at an interval of 0.5-1.0 hour, until the formwork and concrete do not stick together (around 4 hours), and it shall be lifted up 1 course the next day.Special record sheets have been taken for this job for technical controlling of e
24、very item, detailed information see attachment.d.Embedded parts and openings: on the sliding platform, nameplates shall be installed for all the embedded parts and openings and marked the code of embedded parts, size, and elevation data, and one person shall specially manage these nameplates.Attenti
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 生料 库滑模 施工 方案
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,个别因单元格分列造成显示页码不一将协商解决,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【可****】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【可****】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。