1、Erection Program For the 443-3P1preheater towerName of the document:The Erection program of the 443-3P1 preheater towerNo. of the document:GU3-方案-M-010Editing department:The Engineering department of CBMIEdited by:Liu Li Da Date:2023-11-20Verified by: Date:Approved by: Date: Version 0目 录contents一.工程
2、概述 Summary-3 二方案编制依据Compilation basis -3 三吊装机具的选择The choice of Lifting instrument-6 四质量安全保证体系流程图 The flow chart of quality safety guarantee system-11 五施工工艺过程 The construction process-12六安全及文明施工Safe and civilized construction-16一工程概述Summary:HOLCIM(ECUADOR)GU3水泥厂是一条日产4500吨的水泥熟料生产线。窑尾预热器塔架是整个熟料生产线的关键部位
3、,因其系统复杂,安装高度高,构件数量多,单件重量重而成为安装难度最大的一个子项之一。预热器塔架采用钢结构和预热器相结合的安装方式,其中钢结构的的作用是支撑整个预热器系统,提供生产操作,检修操作的平台。整个钢结构主体系统共7层,高96.4m(15m-111.4m),构件共9根H型钢,各层平面有连接梁,上铺花纹钢板,钢结构总重约2500吨。预热器在熟料生产中重要起生料预热和物料分解的作用,整个系统分别由五级旋风筒、分解炉、三次风管、喂料室等组成,设备安装分别从喂料室开始至C1旋风筒结束。预热器系统还配备有提高机、喂料机、风机、收尘器,电梯等辅助设备。HOLCIM (ECUADOR) GU3 Cem
4、ent is a 4500 t/d clinker cement production line. Preheater tower is the key component of clinker production line, because of its complexity, the installation height is high, the number of multi-component, one-piece heavy weight and become difficult to install one of the largest one child. Preheater
5、 tower using a combination of steel and installation, which is the role of steel structures to support the entire preheater system, providing production operations, maintenance operations platform. Entire steel body system of 7 storey, 96.4m (15m-111.4m), member of 9 H-beam, the beam is connected pl
6、anar layers, upper tread plate, steel structure weighing about 2,500 tons. Preheater in the clinker production mainly from the decomposition of raw material preheating and the role of the entire system respectively, by five cyclone, calciner, tertiary air duct, feed room and other components, equipm
7、ent installation separately from the feed chamber begins - C1 cyclone ends. Preheater system is also equipped with bucket elevator, feeder, fan, dust collector, elevators and other auxiliary equipments.二 编制依据Compilation basis1. HOLCIM(ECUADOR)GU3水泥厂烧成窑尾工艺布置图。 HOLCIM(ECUADOR)GU3 PROJECT PREHEATER TOW
8、ER GENERAL ARRANGEMENT DRAWING工 艺 布 置 图General arrangement drawing2. HOLCIM(ECUADOR)GU3水泥厂窑尾塔架钢结构制作、安装图。 HOLCIM(ECUADOR)GU3 preheater tower steel structure fabrication, installation drawings3. HOLCIM(ECUADOR)GU3水泥厂预热器制作、安装图。HOLCIM(ECUADOR)GU3 preheater fabrication, installation drawings4. 钢结构施工验收规范S
9、teel construction and acceptance。5. 机械设备安装验收规范Mechanical equipment installation acceptance。三.吊装机具的选择The choice of Lifting instrument:窑尾预热器塔架的安装重要涉及预热器的地面组对工作和钢结构预热器的高空安装工作。钢结构、预热器的安装工作由于构件安装高度高,整个安装面积大,如使用大型可移动吊车将存在吊装高度不够,吊装性能小的问题,并且施工速度也很慢。所以我们将采用STT403-24T型塔吊。地面预热器的组对将使用一台50吨吊车。下面是STT403-24T塔吊的性能表
10、和预热器塔塔吊的布置图。Preheater tower installation includes preheater ground group work and steel preheater aerial installation work. Steel structure and the installation of the preheater components mounting height is high, the entire installation area, if using the large mobile crane, the lifting will be not
11、 high enough and the less lifting capacity, and the construction speed is very slow. So we will use STT403-24T type crane. Ground preheater group will use a 50-ton crane. Here is STT403-24T crane performance tables and preheater tower crane layout.STT403-24T塔吊吊装性能表STT403-24T Tower crane performance
12、tableSTT403-24T塔吊载荷信息表STT403-24T Tower crane load chart 塔 吊 布 置 图 Preheater tower crane layout通过对预热器塔钢结构重量的计算,前两层钢结构的单件重量达20吨。结合塔吊的吊装性能标和塔吊的布置图可以看出:使用STT403-24T塔吊进行预热器塔的安装施工满足不了施工规定,固需要250吨吊车配合吊装。Through the preheater tower steel structure weight calculation, all steel single piece weighing not more
13、 than 12 tons. Combined with crane and crane lifting performance standard layout can be seen: Use STT403-24T preheater tower crane for installation and construction fully meet the construction requirements四Flow Sheet for Guarantee System of Quality and Safety 质量安全保证体系流程图主管经理Mananger:Zhouyougen质量安全:Q
14、uantity and safety:BowenshuaiDucumentation:Zhangqing Tech director:Zhu ziwuSupervisor:Xue zhiminXiang xianlunLiftingZhangjieChenlabaoDocumentation record and storageSAFETT SUPERVISOR:YANGHAICHAOthe bridge work execute(50 workers)五.施工工艺过程 The construction processitemtimeactivitymethodtoolsNumber of w
15、orkersNumber of people aroundFeed-end chamber erectionStart:25/12/13End:10/01/14Size(m)Width:5.15mHeight:8.6mLength:2.55mWeight:16.9ton1. Assemble all the parts on the ground.2.lifting feed-end chamber 3.Stairs erectionTower craneArc welderChain blockLength ruler4515itemtimeactivitymethodtoolsNumber
16、 of workersNumber of people around+16.000-27.000m column and frame girder erectionStart:10/01/14End:25/01/14Column max.size(m):Length:12.4mGirder max size(m):length: 11mSingle part weight: 5.5ton1.Nine columns erection2.Frame girder erection.Tower crane,Arc welder,Chain block,Theodolite,Length ruler
17、,Electric wrench4515+27.000m sub-girder and platform erectionStart:26/01/14End:31/01/14Sub-girder size(m):Length: 10mSingle part weight: 5ton1.Pipe erection2. +27.000m plan sub-girder erection3.+27.000m platform erection4.Stairs erectionTower craneArc welderChain blockTheodoliteLength rulerElectric
18、wrench4515bottom section Precalciner erectionStart:01/02/14End:02/02/14Size(m)diameter:4.616-6.416mLength:16.174mWeight:20.05tonFirst lift weight:7.5 tSecondly lift weight:14.05 t1. Assemble two parts according to sketch map on the ground.2.lifting first lift3.lifting secondly liftTower craneArc wel
19、derChain blockLength ruler4510+27.000-41.600m column and frame girder erectionStart:03/02/14End:13/02/14Column max.size(m):Length:14.6mGirder max size(m):length: 11mSingle part weight: 8 ton1.Nine columns erection2. Frame girder erection.Tower craneArc welderChain blockTheodoliteLength rulerElectric
20、 wrench4015+41.600m sub-girder and platform erectionStart:14/02/14End:20/02/14Sub-girder size(m):Length: 11mSingle part weight: 4 ton1.Pipe erection2. +41.600 plan sub-girder erection3.+41.600m platform erection4. Stairs erectionTower craneArc welderChain blockTheodoliteLength rulerElectric wrench45
21、15middle section Precalciner erectionStart:21/02/14End:28/02/14Size(m)diameter:5.646-6.416mLength:8.57mWeight:20.05 tonThirdly lift weight:8.5 tonFourthly lift weight:11.55 ton 1. Assemble two parts according to sketch map on the ground.2.lifting thirdly lift3.lifting fourthly liftTower craneArc wel
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 施工 方案
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,个别因单元格分列造成显示页码不一将协商解决,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【丰****】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【丰****】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。