施工现场协调管理(英文)模板.doc
《施工现场协调管理(英文)模板.doc》由会员分享,可在线阅读,更多相关《施工现场协调管理(英文)模板.doc(13页珍藏版)》请在咨信网上搜索。
1、V. Construction Site Coordination Management1. Construction General Layout Plan CoordinationBased on construction deployment and milestone delivery requirements in various phases, General Contractor is in charge of formulating overall plan for general layout plan and deliver technical disclosure to
2、subcontractors for carrying out dynamic management.General contractor is responsible for dispatching road, temporary storage yard, fixed storage yard within construction site unitedly.The subcontractor shall submit “temporary access road or storage yard application sheet to General contractor as per
3、 production requirements at each stage for approval by procedures.The subcontractor shall submit “Use of existing fixed storage yard application sheet” (Sheet 7-2) to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors ar
4、e responsible for standardized management and maintenance of public facilities, surrounding roads within fixed storage yard or temporary site they used, as well as to cater for General Contractors standardized management requirements.2. Temporary Water and Power Supply CoordinationGeneral Contractor
5、 is in charge of overall planning and implementation for temporary water and power supply deployment and deliver technical disclosure to subcontractors.The subcontractors are in charge of configuring full-time temporary water and power supply managerial personnel, who should submit to General Contra
6、ctor “Subcontracting use power general schedule” within stipulated period, as well as to sign “ Temporary water and power use management agreement” with General Contractor within one week.The subcontractor shall submit “Use of temporary power supply application” to General Contractor Production Coor
7、dination Department as per production requirements at each stage for approval.The subcontractors are in charge of safety management of temporary water and power use and accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immedi
8、ately.3. Temporary Facilities CoordinationGeneral Contractor is in charge of overall planning and implementation for temporary facilities, formulating usage allocation scheme and deliver technical disclosure to subcontractors.The subcontractor shall submit “Use of temporary facilities (office, livin
9、g) application sheet” to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors are in charge of maintain and manage temporary facilities use and accept daily inspection from General Contractor, as well as rectify the discov
10、ered problems during inspection and make reply immediately.The subcontractors are in charge of applying overall acceptance and handover to General Contractor after temporary facilities usage completed.4. Material and Equipment Mobilization and Demobilization Coordination The subcontractors shall sub
11、mit detailed material, equipment mobilization application schedule in accordance with General Contractors construction progress to confirm material, equipment name, specification, model and mobilization time.The subcontractors are in charge of material mobilization and demobilization, who shall prep
12、are documents which include, but not limited to, material type, transportation mode, quality assurance, etc. as well as submit “Material/equipment mobilization and demobilization application sheet” to General Contractor Production Coordination Department for approval.The subcontractors are in charge
13、 of abide by General Contractors site material and equipment management system, pile up mobilized material and equipment in good order, accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immediately.5. Vertical Transportation
14、CoordinationGeneral Contractor is in charge of overall planning and implementation for vertical transportation equipment, formulating project vertical transportation scheme and deliver technical disclosure to subcontractors.The subcontractors shall submit “ Subcontract vertical transportation equipm
15、ent use schedule sheet” to General Contractor for approval.The subcontractor shall submit “Use of vertical transportation application sheet” to General Contractor Production Coordination Department every day as per daily construction demand for approval.General Contractor is in charge of planning al
16、l subcontractors vertical transportation equipment use situation as a whole and formulating and public “Daily use distribution sheet of vertical transportation equipment” , as well as coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment.The subcon
17、tractors are in charge of configure full-time staff to manage vertical transportation within subcontractors and cooperate General Contractor to coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment.General Contractor is in charge of arranging verti
18、cal transportation equipments keep and maintenance, attachment, jacking time reasonably and give to publicity timely.6. Public Operation Platform CoordinationGeneral Contractor is in charge of formulating overall plan for public operation platform and deliver technical disclosure to subcontractors i
19、n accordance with contract organization or entrust subcontractors to erect, dismantle and maintain public operation platform.The subcontractor shall submit “Dismantle of public operation platform application sheet” to General Contractor Production Coordination Department for approval due to the need
20、 of altering, dismantling platform, dismantle shall be conducted only after obtained the approval, which could be used only after inspection and acceptance of dismantling and alteration.General Contractor is in charge of supervising public operation platforms use condition, handling misuse timely.7.
21、 Public Security Protection CoordinationGeneral Contractor is in charge of unifying public security standard in accordance with contract organization or entrust subcontractors to fit with public security protection facilities, as well as deliver technical disclosure to subcontractors.General Contrac
22、tor is in charge of public security protection and supervision within public area, the subcontractors are responsible for security protection and supervision within working face.The subcontractor shall submit “Dismantle of public security protection application sheet” to General Contractor Productio
23、n Coordination Department for approval due to the need of altering, dismantling safety protection, dismantle shall be conducted only after obtained the approval, which could be used only after inspection and acceptance of dismantling and alteration.General Contractor is in charge of managing securit
24、y protection in construction site as a whole, as well as execute supervision and acceptance works for safety protection dismantling and alteration.8. Site Elevation Axis CoordinationGeneral Contractor is responsible for preparing overall survey control scheme, establishing Level 1 plane and vertical
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 施工现场 协调 管理 英文 模板
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【快乐****生活】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【快乐****生活】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。