中英文对照施工方案.doc
《中英文对照施工方案.doc》由会员分享,可在线阅读,更多相关《中英文对照施工方案.doc(9页珍藏版)》请在咨信网上搜索。
1、你一定要坚强,即使受过伤,流过泪,也能咬牙走下去。因为,人生,就是你一个人的人生。=中英文对照施工方案目 录Contents1. 工程概况 General2. 编制依据 References3. 施工顺序 Construction Sequence4. 施工方法 Construction Method5. 安全与环境保护施工措施 HSE6. 劳动力计划 Manpower Mob. Schedule7. 机具计划 Equipment/Tools Mob. Schedule8. 施工作业计划 Construction Schedule1. 工程概况General该项目为珠海PTA二期工程,本方案主
2、要是为PTA二期变电所结构而编制的施工技术措施。主体结构三层钢筋砼框架,局部为二层钢筋砼框架结构,变压器区域采用钢筋砼墙体。This method statement is compiled to describe the substation structure construction method of Zhuhai PTA No.2 Project, which major structure is three-layer reinforced concrete frame and partial structure is two-layer reinforced concrete f
3、rame and transformer area is reinforced concrete wall.2. 编制依据References2.1. 施工图纸 Construction Drawings REV.2 6092-BCO.01-DW-1741-01 to 25 2.2 工程测量规范Code for Engineering Surveying GB50026-93 2.3 混凝土结构工程施工质量验收规范 Code for Quality Acceptance for Concrete Structure GB50204-20022.4 混凝土泵送技术规程 Technical Cod
4、es for Concrete Casting by Concrete Pump JGJ/T10-952.5 建筑工程施工质量验收统一标准 Unified Standard for Construction Quality Acceptance of Construction GB50300-20012.6 钢筋焊接及验收规程 Code for Acceptance of Re-bar Welding JGJ18-20032.7 建筑施工高处作业安全技术规范 Safety Technical Code for Work at Height During Construction JGJ80-9
5、12.8 施工现场临时用电安全技术规范 Electricity Safety Technical Code for Temporary Power Supply on Construction Site JGJ46-882.9 混凝土强度检验评定标准 Assessment and Acceptance for Concrete Strength GBJ107-873. 施工顺序 Construction Sequence4. 施工方法 Construction Method 4.1脚手架工程Scaffolding work4.1.1 框架外的双排脚手架由架业公司搭设。Double scaffo
6、ld outside the structure will be built by scaffolding company.4.1.2梁和板底搭设满堂脚手架。脚手架立杆基土应平整、密实,且所有立杆底部应加设宽度大于200mm,厚度大于50mm,长度4m的垫木。Full scaffold shall be used for beam and slab bottom. Pole foundation soil shall level and dense, and size more than 4m(L)200mm(W)50mm(T) wood block shall be set for all
7、pole bottom。4.1.3满堂脚手架的立杆间距1.2m,横杆间距为1.6m。每隔12m设置一道剪力撑。搭设方法见下图。立杆与纵、横向扫地杆连接固定,纵横向立杆应在同一条直线;纵、横杆搭接接头不要大于50,即杆件接头要错位搭接。立杆搭设时应通过吊垂线保证其垂直度,垂直误差不得大于20mm。 Spacing between poles of full scaffold is 1.2m, and set cross bridging for every 12m, and method please see following sketch. Poles shall be erected as
8、 per the location, and fasten the poles with longitudinal and transverse bottom pole, and longitudinal and transverse poles shall be at the same straight line. Overlap junctions of longitudinal and transverse poles shall be not more than 50%, that is, pole junctions shall be overlapped staggered. Ve
9、rticality shall be ensured by plumb line when, and tolerance of verticality shall be not more than 20mm.4.1.4端头各设置一道剪刀撑,每道连接不少于4根立杆,纵向轴线除两端各设置一道剪刀撑外,按间距12m设置剪刀撑;剪刀撑接长必须用搭接,且搭接长度不小于1m,转扣不少于3个,每组剪刀撑的宽度不小于4跨,且不小于6m,斜杆与地面的夹角4560 Cross bridging shall be installed at the ends of transverse axis, and each
10、connection shall be not less than four poles. Besides cross bridging installed at the ends of the longitudinal axis, it also installed as per 12m spacing. Overlap must be used for cross bridging spreading, and overlap length shall be not less than 1m, and rotary button shall be less than three, and
11、each cross bridgings width shall be not less than four spans and shall be not less than 6m. Separation angle between diagonal pole and ground is 4560.4.1.5 脚手架平面布置及上下通道平面位置见附图1。 Make the sketch for detail plane of scaffolding including access way. Please see sketch No.-1.4.1.6脚手架搭设好后,必须经过IPMT/CFCS/H
12、SSE验收合格后方可投入使用。 After completion of scaffolding work, it must be inspected and accepted by IPMT/CFCS/HSSE. 4.2模板工程 Formwork4.2.1梁、柱和墙板采用=18mm的胶合模,板采用组合钢模板。48*3.5的标准脚手架钢管加固。模板安装前,应将模板面残留砼清理干净、且在钢模板上均匀涂刷隔离剂。 =18mm plywood form shall be used for beam, column and wall, and combined form shall be used fo
13、r base slab, and reinforced by 48*3.5 scaffold steel pipe. Forms shall be cleaned and remove the residual concrete, and also separant shall be painted on the steel form evenly before form installation.4.2.2柱模板Column form 1)安装顺序:柱轴线投点、放支模线搭设柱四周井字架控制标高绑扎柱钢筋、墙拉结筋、安放钢筋保护层垫块拼装柱模板柱模板校正并加固Installation sequ
14、ence: mark out the column axis and form linebuild “井” shape rack around the columncontrol elevationcolumn rebar work, wall binding rebar work, install the cushion blockinstall the column formcolumn form adjustment and reinforcement2)将柱轴线、标高线复测投点,弹出柱支模线,将柱脚支模处用1:2 水泥砂浆找平,每根柱周围搭设井字架,在井字架上抄测标高控制线。Resur
15、vey the column axis and elevation line, and mark out the column form line, 1:2 cement mortar will be used to leveling at the column bottom. “井” shape rack will be set around each column, and mark elevation control line on it.3)绑扎柱筋,垫保护层垫块,安放埋件、墙拉结筋。Column rebars and cushion block work, install the s
16、teel inserts and wall binding rebar.4)经检查合格并办理隐蔽检查记录后拼装柱模。柱根部留设清扫口。柱与梁的模板安装如附图1所示。Column form will be installed after inspected & accepted and got the concealed work inspection record. Cleanout shall be set at the bottom of column bottom. Details of the column and beam form installation please see a
17、ttached sketch No.-1.5) 柱箍采用48*3.5双钢管背棱,柱箍间距400mm;柱底及柱顶均应设置柱箍,柱加固图见附图2。用钢管与脚手架有效连接并固定、校正。柱底部用1:2水泥砂浆堵缝防止漏浆。 48*3.5 double steel pipe heel will be used for the column hoop, and spacing between column hoop is 400mm. Steel pipe shall be used to connect the scaffold and fixing and aligning. 1:2 cement m
18、ortar will be used to seal the column bottom to prevent leakage. Column hoop shall be installed at the column bottom and top, details about reinforcing please see attached sketch No.-2. 6)柱模安装基本完毕后对断面尺寸、轴线、标高、垂直度等进行全面检查校正后再进行固定,并将各柱井字架之间连成一体,形成稳定整体结构。After column form installation, overall inspectio
19、n and aligning shall be done for the cross dimension, axis, elevation and verticality, and then connect each column “井” shape rack as overall stable structure. 4.2.3梁、板模板Beam and slab form1)安装顺序:抄测量控制标高搭梁底模双排架及板底满堂脚手架安装梁底模绑扎梁钢筋、安放垫块安装梁侧模校正加固模板拼装板底模绑扎板钢筋Installation sequence: mark out the control ele
20、vation double scaffold of beam bottom form and full scaffold of slab bottom beam bottom form installation beam rebar and cushion block work beam side form installation form adjustment and reinforcement slab bottom form installation slab rebar work2)在梁模下搭设双排钢管立柱承重架,钢管立柱采用48钢管,立杆纵向间距为750mm。Pole bearin
21、g rack with double steel pipe shall be built under the beam form, 48 steel pipe will be used for the pole, and longitudinal spacing between poles is 750mm. 3)梁高在800mm1000mm的梁中部设对拉螺栓一道,梁高为1200mm的梁设置两道对拉螺栓。对拉条安装方法见附图3,在模板拆除对拉螺栓拿出后,采用微膨胀水泥砂浆封堵。1200mm高梁模板支设计算书附后。One set pull bolt shall be installed at t
22、he middle of beam while the beam is 800mm to 1000mm, and two sets pull bolt will be installed while the height is 1200mm. Details about the installation please see attached sketch No.-3. Expended cement mortar shall be used for sealing after form dismantled and pull bolts removed. For 1200mm height
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 中英文 对照 施工 方案
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,个别因单元格分列造成显示页码不一将协商解决,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【胜****】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【胜****】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。