1、1. Which is one of the six aspects of project performance that needs to be managed?a. Accuracyb. Reliabilityc. Scoped. Ease of use2. What theme ensures the project is desirable, viable and achievable?a. Organizationb. Progressc. Business Cased. Risk3. What process is triggered by the project manager
2、s request to initiate a project?a. Starting up a Projectb. Initiating a Projectc. Directing a Projectd. Managing a Stage Boundary4. The purpose of what theme is to establish mechanisms to monitor and compare actual achievements against those planned?a. Business Caseb. Changec. Progressd. Quality5. W
3、hich is an objective of the Closing a Project process?a. Check that all the projects products have been accepted by the usersb. Prepare for the final stage of the projectc. Capture the customers quality expectationsd. Ensure that all benefits have been achieved6. Identify the missing words in the fo
4、llowing sentence.A purpose of the Managing a Stage Boundary process is to provide the Project Board with sufficient information so that it can approve the ? for the next stage.a. Work Packagesb. Exception Reportc. Stage Pland. Project Brief7. What theme provides information on what is required, how
5、it will be achieved and by whom?a. Organizationb. Plansc. Business Cased. Quality8. Which is recommended as a possible risk response type for an opportunity?a. Reduceb. Transferc. Rejectd. Fallback9. Basing projects on a management by exception principle provides which benefit?a. Promotes consistenc
6、y of project work and staff mobilityb. Provides a common languagec. Clarity of what a project will deliver, why, when and by whomd. Efficient and cost-effective use of management time10. Identify the missing words in the following sentence.The purpose of the ? process is to establish solid foundatio
7、ns for the project, enabling the organization to understand the work that needs to be done to deliver the projects products.a. Initiating a Projectb. Starting up a Projectc. Directing a Projectd. Managing a Stage Boundary11. Which is a purpose of the Managing Product Delivery process?a. Controls the
8、 link between the Project Manager and the Team Manager(s)b. Tracks the progress of a stage with the help of Checkpoint Reportsc. Provides a link between the work of the Project Manager and the Project Boardd. Maintains a focus on the delivery of benefits throughout the stage12. Which role is respons
9、ible for authorizing and monitoring work to be completed and for taking corrective action within a stage?a. Project Managerb. Project Supportc. Project Assuranced. Team Manager13. Which fact is true for Project Assurance but not quality assurance?a. Responsible for monitoring the conduct of the proj
10、ectb. Independence of the Project Managerc. Appointed as part of the project management teamd. Responsible for reviewing the project for compliance with corporate standards14. Which is NOT a characteristic of a project?a. Has a higher degree of risk than business as usualb. Involves people with diff
11、erent skills introducing a change that will impact others outside of the teamc. Has a lifespan that usually covers the delivery of the desired outcomes and the realization of all the expected benefitsd. A temporary management structure created for the implementation of business products15. What prod
12、uct forms the contract between the Project Manager and the Project Board for the project?a. Project Planb. Project Product Descriptionc. Project Initiation Documentationd. Project Brief16. Which is an objective of the Managing a Stage Boundary process?a. Enable the Project Board to commit resources
13、and expenditure required for the initiation stageb. Review and, if necessary, update the Project Initiation Documentationc. Provides a break between those managing the project from those creating productsd. Ensure a periodic review is held to approve the products created within the completed stage17
14、. How should a Team Manager escalate a suggestion for an improvement to a product?a. Include details in a Checkpoint Reportb. Include details in a Highlight Reportc. Raise an issued. Raise an Exception Report18. Which is a purpose of the Closing a Project process?a. Define the procedure for handing
15、over productsb. Provide a fixed point at which acceptance for the project product is confirmedc. Define formal requirements for the acceptance, execution and delivery of project workd. Confirm all project benefits have been achieved19. Which is an objective of the Starting up a Project process?a. Co
16、nfirm there are no known restrictions that would prevent the project from being deliveredb. Ensure all Team Managers understand their responsibilitiesc. Get approval for the Project Plan from corporate or programme managementd. Prepare the Project Initiation Documentation for authority to initiate t
17、he project20. What process is used to provide an interface with corporate or programme management?a. Managing Product Deliveryb. Directing a Projectc. Controlling a Staged. Managing a Stage Boundary21. Which is NOT a purpose of an End Project Report?a. Compare project achievements against what was o
18、riginally agreedb. Record information that will help future projectsc. Prompt the Project Board to authorize the next staged. Pass on details of any ongoing risks for those who will maintain and operate the finished product22Identify the missing word(s) in the following sentence. If a baselined prod
19、uct requires modification, the ? procedure should be applied in order to manage the modification.a. Risk managementb. Exceptionc. Issue and change controld. Quality control23. Which is a purpose of a Project Brief?a. Describe an agreed position from which the project can be startedb. Describe the in
20、formation needs of the projects stakeholdersc. Describe the configuration management that will be used by the projectd. Describe the reporting requirement of the Project Board24. Which is one of the four integrated elements within PRINCE 2?a. Qualityb. Role description c. Processesd. Product Descrip
21、tion25. Which of the following statements apply to a Stage Plan?1. Is produced with the knowledge of earlier stages2. Provides the basis for control by the Project Board3. Is produced close to the time when the planned events will take place4. Provides the basis for day-to-day by the Project Manager
22、a. 1, 2, 3b. 1, 2, 4c. 1, 3, 4d. 2, 3, 426. Identify the missing words in the following sentence?Because the Project Board receives regular ?, there is no need for regular progress meetings.a. End Stage Reportsb. Checkpoint Reportsc. Exception Reportsd. Highlight Reports27. Which is a benefit of usi
23、ng the product-based planning technique?A. All the required products of the project will be delivered to time and to costB. Clearly shows how long a project will takeC. It removes the need for activity-based planningD. Reduces the risk of incorrectly scoping the project28. Which of the following sta
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- Prince2 测试 试题
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【精****】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【精****】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。