1、(完整word)研究生外文文献翻译-中英完整版Discussion about the application of the anchor bar on the slope constructionFu Ming Fu , Zhang TianAbstract: There are some advantages in strengthening slope with the anchor bar, such as low project cost, convenient for construction and so on。 It not only meets the requirement
2、 of the reliability of the construction, but also is economic and reasonable for the construction.Key words: anchor bar; slope; strengthening1. Introduction Anchor technique uses strata geotechnicals shear strength around bolt to deliver structures pulling force or keep strata of the excavation own
3、stability. Due to the use of the anchor rod, Anchor strata produce compressive zone and have reinforcement effect to strata, can enhance the strength of strata, improve mechanical properties of strata, make structure and stratum together formed a kind of work together complex. Anchor system can effe
4、ctively sustain tension and shear, improve shear strength of the potential sliding surface, so it can effectively prevent slope to produce sliding damage. Fig 1 after excavation of the slope2. Project profile The length of a slope is about 60m, the most slope height is about 23m,the angle up to 50 7
5、5, a five-layer frame structure buildings is far from about 1.5 to 4m at its base edge, its foundation is artificial bored pile and its bearing stratum is in weathered phyllite。 Due to the strong weathering of rocks, it was chunky, loosely structured, multimuddy filling。 It has residual slope deposi
6、ts of silty clay overlying and local folder with a pulpy, low strength。 Slope had collapsed at various locations, it is vary dangerous to the building, so we need to reinforce the slope, and we use stone concrete retaining wall and bolt to support it。3. Bolt retaining and protecting design3.1 Bolt d
7、esign(1)all formation of anchor use whole length bond-type, the binder materials are ordinary cement mortar, the mortar strength grade is M30, the anchor length L is 10 meters, the slope height h is 9 meters. Anchoring section length is 5m。(2)According to the construction condition and the needs of
8、the process, the layout form of anchor use quincunx, and in order to make the anchoring force in the role of surface rock surface with uniform, the two adjacent line bolts should be staggered arrangement.(3)The anchors number according to h/3.24 per meter to calculation, the anchor length is L, a to
9、lal of 252。 The diameter of drilling holes is 90,the number of drill according to (L0。1)m per hole to calculation, M30 grout number according to average 0。052m3 per hole to calculation。(4)The two adjacent rows vertical spacing of anchor take 2.55m, horizontal spacing take 2。55m。 The dip angle of anc
10、hor: with the angle of horizontal line is 20, and drilling down with this Angle.(5)Anchor use the steel bar, which is HRB400 level, 28mm diameter。3.2 Anchor calculation (1)The calculation of lateral geotechnical pressure12When the supporting structure to leave in rock and earth mass direction migrat
11、ion until to the limit equilibrium state, the geotechnical pressure which is role in supporting structure called active geotechnical pressure。 Its calculation method is as follows:For the slope which has no flare structure surface, generally speaking, failure is controled by rock mass strength, the
12、calculation formula is same to the active soil pressure, but cohesive force C take zero, internal friction angle use (rock mass equivalent internal friction angle) instead of, according to the standard to selection; rupture angle is 45+/2(is rock mass internal friction angle, is estimationed by hair
13、cut at the standard of rock mass internal friction angle, reduction factor according to the standard to selection)。According to the engineering survey, active rock pressure can calculation as follows:(2)the calculation of anchor tension design value (1) (2)In the formula: is anchor tension design va
14、lue; is anchor tension standard value; is partial load factor, take 1。3; is the horizontal tension standard value of anchor; is the dip angle of anchor。Through the calculation, =112.3kN =145。99kN(3)the calculation of anchor steel section area (3)In the formula: is the steel section area of anchor; i
15、s slope engineering importance coefficient(the slope engineering importance coefficient of this project is level 1, take 1.1); is the tensile working conditions coefficient of anchor bar ( permanent anchor take 0.69, temporary anchor take 0。92); is the tensile strength design value of anchor bar(sta
16、ndard value=400, design value=360)。According to the calculation, 0。588,choose level 3 steel of 128mm, =0.615。(4)The calculation of anchorage body and rock mass anchoring lengthanchoring length should not only meet the requirements which the bond force of formation on mortar and the bond stress of mo
17、rtar on steel, but also meet the requirements that the Structure design codes the Minimum anchoring length. (4)In the formula: is the anchoring length; D is the diameter of anchorage body; is the bond strength eigenvalue of layer and anchorage body, through the experiment or local experience sure, o
18、r according to the standard to selection ( this engineerings rock mass uniaxial compressive strength is 7。46, belong to soft rock, rock mass structural plane development, take 300);is the bond working conditions coefficient of anchorage body and layer (permanent anchor take 1.00). According to the c
19、alculation, 4.3m, take=5。0m.(5)The anchoring length between anchor steel and anchor mortar (5)In the formula: is the anchoring length between steel and mortar; d is the diameter of anchor bar; n is the number of steel; is the bond strength design value between steel and anchor mortar, through the ex
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 研究生 外文 文献 翻译
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【精****】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【精****】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。